Welcome to the Salmon Arm Golf Club Turfcare Blog. With this blog we will be able to provide more up to date information regarding the operations of our golf courses at the SAGC. If you have any questions or concerns please feel free to submit a comment or email our Master Superintendent directly at tkubash@salmonarmgolf.com



Monday, October 8, 2012

Drill and Fill Procedures

During the month of October we will be using our drill and fill machine to remediate the rootzone of some of the Champions Course's greens. Specifically #3-11 and #16

We will work on one green a day Monday through Friday, and hope to finish prior to the 11 shotgun. It will usually take 3-4 hours to complete a green. It is possible however that we are still working on a green when the shotgun commences. If this occurs we ask that you play the temporary pin location for that hole.

Thank you for your understanding, your assistance helps all of us make the SAGC a better place.